2009年项目管理专家资格认证考试(PMP)模拟题

项目管理专家资格认证考试(PMP)2009年模拟题

1.Which of the following is true about accuracy and precision?

A. Precision is consistency and accuracy is correctness

B.Precision is correctness and accuracy is consistency

C.Precision and accuracy are same

D. Precision is used for measuring length and accuracy is used for time measurements

Your

下列哪个关于正确度和精确度的说法是正确的?

A.精确度是说连续性;正确度是说是否符合事实

B.精确度是说是否符合事实;正确度是说连续性

C.精确度和正确度是一样的

D.精确度用来测量长度;正确度用来测量你的时间

2.Which process group is associated with schedule control, scope control, and cost

control

A. Monitoring and Controlling

B. Planning

C. Executing

D. Closing

哪个过程组包括进度控制,范围控制和成本控制?

A.监控项目

B.规划

C.执行

D.收尾

3.In Probability and Impact Metrics which of the following statement is true?

A. For opportunities, the high risk (dark grey) zone offers greatest benefits

B. For opportunities, the low risk (medium grey) zone offers lowest risk and best benefits

C. for Risks the high risk (dark grey) zone offers greatest benefits

D. for Risks the low risk (medium grey) zone should be addressed first

关于概率和影响矩阵,下列哪个说法是正确的?

A.对机会而言,高风险(黑灰色)区域意味着代表最大的利益

B.对机会而言,低风险(中灰色)区域意味着最低的风险和最好的利益

C.对风险而言,高风险(黑灰色)区域意味着最大的利益

D.对风险而言,低风险(中灰色)区域应该必须首先确定

6.Purchase order is the simplest example of _________ type of contract

A.T&M Contract

B. Fixed Price

C. Cost plus Incentive Fee

D. Cost plus Fixed Fee

采购单是什么类型合同的例子?

A.时间材料合同

B.固定价格

C.成本加奖励费用

D.成本加固定费用

7.You are the project manager in East West Construction Company. After the completion

of the structure you are visiting the site and checking whether the construction is as per the

plan by taking the measurements. This is an example of

A. Risk Identification to prevent issues in the future

B. Active project management

C. Quality Assurance activity – Prevention

D. Quality Control Activity – Inspection

你是东西建筑公司的项目经理。在完成建筑后,你到实施地点检查是否建筑按照计划进行了测

量。这是什么的例子?