pmp考试模拟题(600题)

The highest degrees of project risk and uncertainty are associated with the following phase of the project: conceptual execution cut-over post project evaluation A and D only A
The most common types of schedules are Gantt charts, milestone charts, line of balance, and: Networks. Time phased events. Calendar integrated activities. A and C only. B and C only. A
Which of the following is of