PMP模拟题2009
156.Your procurement department has obtained independent estimates. The vendor s
proposal is substantially different than the independent estimates. All of the following are
true except:
A. The SOW was not detailed enough
B. The vendor failed to respond according to the terms of the proposal
C. The vendor failed to respond to all items in the SOW