Mr.Bank

国际注册项目管理师(PMP)资格认证考试2009年模拟考试题(一)

国际注册项目管理师(PMP)资格认证考试2009年模拟考试题(一)及答案下载

6.Purchase order is the simplest example of _________ type of contract

A.T&M Contract

B. Fixed Price

C. Cost plus Incentive Fee

D. Cost plus Fixed Fee

采购单是什么类型合同的例子?

A.时间材料合同

B.固定价格

C.成本加奖励费用
D.成本加固定费用

7.You are the project manager in East West Construction Company. After the completion

of the structure you are visiting the site and checking whether the construction is as per the

plan by taking the measurements. This is an example of

A. Risk Identification to prevent issues in the future

B. Active project management

C. Quality Assurance activity – Prevention

D. Quality Control Activity – Inspection

你是东西建筑公司的项目经理。在完成建筑后,你到实施地点检查是否建筑按照计划进行了测
量。这是什么的例子?

A.风险识别用来防止未来出现的问题;

B.动态项目管理

C.质量保证活动-预防

D.质量控制活动-检查

8.You are in charge of installing a Voice Response System for a major company. You are

about to start preparing the estimates and the Sponsor informed you that the estimate

should be as much close to reality as possible. Which of the following you will most likely

to use for your estimation:

A.CPM

B.PERT

C.PDM

D. Monte Carlo Simulation

你在负责为某个大公司安装声音回传系统。你开始准备估算时出资人告诉你估算必须尽可能接

近实际。你最可能使用下列哪个做你的估算?

A.CPM

B.PERT

C.PDM

D.蒙特卡罗模拟


评论

发表回复

您的电子邮箱地址不会被公开。 必填项已用 * 标注